The transportation of equipment for the first section of Zhejiang Petrochemical Phase I, in which our company is involved, is currently underway, including lifting and unloading of loading trucks from the lifting dock, as well as rolling and unloading transportation from ships to the storage yard (installation location in the rolling device area).
The total number of transportation equipment for this project is 730 pieces, with the largest equipment specification of 9400 * 35000 and a weight of 400 tons& nbsp; During the National Day holiday, our colleagues worked hard to transport a total of 15 pieces of equipment on the island, currently completing about 45% of the total.