Zhejiang Petrochemical 40 million tons/year integrated refining and chemical project

Zhonglian Haiguangying Logistics Engineering Co., Ltd  2018-10-06 projectdynamic

Our company successfully completed the roll on/roll off transportation of two adsorption towers in the eighth batch of the Zhejiang Petrochemical Equipment Transportation Project on October 20th. The highly anticipated 40 million ton/year integrated refining and chemical project of Zhejiang Petrochemical is proceeding safely as always. The project team is closely planning and preparing everything for the transportation of the largest equipment in this project - the three in one unit module for reorganization. 

The Zhonghai Guangying team successfully completed the roll on/roll off operation at a dock in Nantong on the afternoon of October 6th. They are currently carrying out cargo binding and reinforcement work and are about to sail to the Zhejiang Petrochemical project site. 图片.png

There are a total of two three in one device modules shipped in , with a single weight of 2400t and equipment size of 33x20x42m. Our company has invested a total of 96 axis+4ppu for transportation roll on/roll off operations, and a 12000 ton self-propelled barge is responsible for sea transportation operations& nbsp;  In this project, a total of 12 furnace modules were involved from the initial plan to the smooth implementation of the project, which took more than a year. Through the collaboration and collaboration of multiple departments from China Overseas, Guangzhou, and Ying, a lot of effort was put into ensuring the safe and smooth implementation of the project, providing the owner with efficient and worry free logistics general contracting services throughout the entire process.