Zhejiang Dushan Energy

  Recently, our company completed the annual production of 2.2 million tons of PTA equipment transportation project in Dushan Energy, Zhejiang.he Dushan Energy PTA project in Zhejiang Province will be constructed in two phases, with a planned total investment of 7 billion yuan. It will introduce advanced equipment from both domestic and foreign sources, and adopt industry-leading green and intelligent PTA production technology for its core production devices. It will form an annual production capacity of 2.2 million tons of PTA. 图片.png

  Our company invested suitable vehicles such as SPMT to meet the load requirements and carried out transportation operations for 48 pieces of equipment. Among them, there are a total of 11 pieces of equipment weighing over 300 tons, with the maximum piece being 62m x 9.1m x 9.6m and a weight of 670 tons. All equipment will be transported by floating crane from Pinghu Dushan Port Port and delivered by truck to the project site by road.  图片.png 

The project has been implemented since December 17, 2018, and as of April 30, 2019, 44 pieces of equipment have been transported and completed. Our company has ensured the construction progress of the Dushan Energy PTA project in Zhejiang, setting a record for the largest onshore volume and heaviest tonnage of equipment since the opening of Dushan Port, perfectly showcasing the brand effect and good reputation of Zhonghai Guangying.